Johnson Arabia LLC V Bic Contracting LCC (Formerly Hlg Contracting LLC) [2022] DIFC CFI 075 (08 March 2022)


BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?

No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!

Thank you very much for your support!


BAILII [Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback]

The Dubai International Financial Centre


You are here: BAILII >> Databases >> The Dubai International Financial Centre >> Johnson Arabia LLC V Bic Contracting LCC (Formerly Hlg Contracting LLC) [2022] DIFC CFI 075 (08 March 2022)
URL: http://www.bailii.org/ae/cases/DIFC/2022/DCFI_075.html
Cite as: [2022] DIFC CFI 075, [2022] DIFC CFI 75

[New search] [Help]


CFI 075/2020 Johnson Arabia LLC V Bic Contracting LCC (Formerly Hlg Contracting LLC)

March 08, 2022 court of first instance - Orders

Claim No: CFI 075/2020

THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS

IN THE COURT OF FIRST INSTANCE

BETWEEN

JOHNSON ARABIA LLC

Claimant

and

BIC CONTRACTING LCC
(FORMERLY HLG CONTRACTING LLC)

Defendant


DEFAULT COSTS CERTIFICATE OF THE REGISTRAR NOUR HINEIDI


UPON the Claimant having filed a Notice of Commencement of Assessment on 13 October 2021 (the“NOC”)

AND UPON the Order of the Registrar Nour Hineidi dated 17 January 2022 dismissing the first request for a Default Costs Certificate

AND UPON the second request for a Default Costs Certificate made by the Claimant on 16 February 2022 (the“Request”) pursuant to r. 40.17 of the Rules of the DIFC Court (the“RDC”)

AND UPON the Defendant’s failure to file its Points of Dispute, pursuant to RDC r. 40.15, within 21 days from the date the Claimant served the Defendant with its NOC

AND UPON reviewing the Claimant’s affidavit of service dated 25 February 2022

AND UPON reviewing all other relevant case documents filed in this matter

IT IS HEREBY ORDERED THAT:

1. The Request is granted.

2. The Defendant is ordered to pay the Claimant a total of AED 137,528.81 (the “Amount”) within 21 days from the date of this Order.

3. In the event the Defendant does not pay the Amount within 21 days from the date of this Order, interest, pursuant to Practice Direction No. 4 of 2017 (Interest on Judgments) will accrue on the Amount from 29 March 2022 until the date of full payment.

Issued by:
Nour Hineidi
Registrar
Date of issue: 8 March 2022
Time: 12.30pm